EuroVelo 3

EuroVelo 3
© ADRT Oise-Reed-H.Lenaerts

Aisne

Guise – Ribemont
Development of a 9 km section of cycling route on a dedicated site.

Total budget :
1 203 734€ excluding VAT
ERDF share :
601 867€ excluding VAT

EV3 continuously marked by shared lanes

Finished on  30/09/22

Partner :
Conseil départemental de l’Aisne

  • Guise - Ribemont

    Development of the Eurovélo 3 link along the Oise between Guise and Ribemont with crossings on its own site (9 km) using an old railway line with demolition of a station platform in Bohéries to complete the work done in 2017.

    Infrastructure built on the first third between Guise and Ste Claire since the end of 2020.

    Guise - Ribemont
  • Guise - Ribemont

    Development of the Eurovélo 3 link along the Oise between Guise and Ribemont with crossings on its own site (9 km) using an old railway line with demolition of a station platform in Bohéries to complete the work done in 2017.

    Infrastructure built on the first third between Guise and Ste Claire since the end of 2020.

    Guise - Ribemont

Oise

Pont Sainte Maxence

Development of a greenway link at Pont Sainte Maxence and safety work on the roundabout at Ver-sur-Launette.

Total budget : 283 000€ excluding VAT
ERDF share : 141 500€ excluding VAT

PASSABLE

Finished on 01/06/2018

Partner :
Conseil départemental de l’Oise

  • Pont Sainte Maxence

    Development of a greenway link at Pont Sainte Maxence and safety work on the roundabout at Ver-sur-Launette.

    Finished on 01/06/2018

    Pont Sainte Maxence
    © légende
  • Pont Sainte Maxence

    Development of a greenway link at Pont Sainte Maxence and safety work on the roundabout at Ver-sur-Launette.

    Finished on 01/06/2018

    Pont Sainte Maxence